Formwork quantity calculator
Contact area, plywood sheet count and wall tie positions for walls, slabs, beams and columns.
Concept and estimating tool. Check results and get a design by a qualified engineer for construction. Nothing you enter is stored or sent.
How it works
Contact areas: walls L x H per face; slabs soffit L x W plus edges 2(L + W) x edge depth; beams L x (2 x depth below slab + width); rectangular columns 2(b + d) x H; round columns π D H. Sheets = area x (1 + waste) / sheet area, rounded up. Wall ties are a grid estimate including both ends.
Questions
Does the tie count include end ties?
Yes. The estimate places ties on a grid at the spacing entered, including both ends and the top and bottom rows.
How do I size the ties?
Calculate the design pressure with the concrete pressure calculator, then check the tie load against the tie's working load limit.
Module assistant
Formwork quantity assistant
Type a question about this tool or the site work around it. Answers come from 20 questions written and checked by a Chartered Professional Engineer. No AI, nothing is sent or stored.
Top 20 questions
What does the formwork quantity calculator work out?
It calculates the formwork contact area in m2 for walls, square and round columns, beams and slabs, then converts that area into plywood sheets with waste and a tie count. Use it for estimating, ordering and checking quantities. It does not design the formwork or check loads.
How is wall formwork area calculated?
Wall contact area is two faces x length x height, so 10 m long x 3 m high gives 60 m2. Subtract large openings and add returns, stop ends and any extra faces. Check the height includes the kicker or step, and decide whether the opening area is deducted or left in to allow for edge forms.
How is column formwork area calculated?
For a square or rectangular column, area is perimeter x height. For a round column it is pi x diameter x height. A 0.5 m square column 3 m high has 6 m2 of contact area. Include the face height to the underside of the slab or beam, and note round column forms are usually fibre tube or steel, not plywood.
How is beam formwork calculated?
Beam area is soffit width x length plus two side faces of depth x length. The calculator uses the full depth, so deduct the slab thickness if the beam sides are cut to the slab edge. Take care at beam to column junctions and over-count joints rather than missing them.
How is slab formwork calculated?
Slab area is the soffit area (length x width) plus edge forms (perimeter x slab thickness). Deduct column and opening areas from the soffit if the work is substantial, and add edges around openings. For slabs on ground, only edge forms apply, which is usually much less area.
How are plywood sheets and waste calculated?
The calculator divides the net area by 2.88 m2 per 2400 x 1200 sheet, adds a waste percentage and rounds up. Waste depends on the geometry, so use a higher allowance for cut-heavy work such as small columns and curved forms. The default waste is a starting point, so adjust it from your own site experience.
How is the tie count worked out?
The calculator sets out a tie grid: wall length divided by horizontal spacing plus one, times height divided by vertical spacing plus one, so both ends are included and each through-tie is counted once for both faces. It gives a quantity, not a design. The actual spacing must come from the pressure, tie capacity and waler design, so confirm it with the formwork designer.
What does the calculator not include?
It does not include bracing, soldiers, walers, props, kickers, release agent, fixings, stop ends, chamfers or labour. It also ignores reuse. Add these separately in your estimate or take the allowance from your own cost data, and check them against a formwork design for the job.
How many times can plywood be reused?
It depends on ply grade, face finish, handling, release agent and the concrete finish needed, so there is no fixed number. Common sense on site is to use fresh sheets for the exposed face and keep older sheets for hidden faces. Check the ply supplier and the architectural finish requirements in the specification.
How should I choose between plywood and a proprietary system?
Plywood suits irregular shapes and small quantities. Proprietary panel or table systems suit repetitive work, faster cycles and heavy pressures. Compare cost, crane time, labour and finish. A supplier or an engineer should check capacity for the pressures and the tie layout.
What standard governs formwork design in Australia?
AS 3610.1 Formwork for concrete sets the requirements for design, construction and inspection of formwork, and the WHS framework requires risks to be controlled. The designer should be competent and the formwork should be built as designed. For complex or high load work, get an engineer's design. EcoDesign can prepare a certified design.
What should be checked in a pre-pour formwork inspection?
Check dimensions, level and plumb, tie type and spacing, nuts engaged, bracing, kickers, base fixing, joint sealing, cleanliness, penetrations and cover. Confirm the pour plan and rate of rise match the design. Sign the inspection record before concrete is ordered and fix every defect first.
What are the common causes of formwork failure?
Failures usually come from pouring faster than designed, missing or wrongly spaced ties, inadequate bracing, ply or waler overload, damaged tie components, and poorly supported props. Changes to the design on site without checking are another frequent cause. Always brief the crew on the design limits.
How can I reduce ply waste on site?
Plan panel layouts to full sheet sizes, standardise column and wall dimensions where the design allows, label and reuse off-cuts for infill and kickers, and cut centrally rather than at each location. A cutting list from the estimate helps. Keep an eye on whether the extra planning time is worth it.
How do I estimate stripping times?
Stripping time depends on the concrete strength required before the forms are removed, as set in the specification and the formwork design. Vertical forms often come off earlier than soffit forms and props. Do not use a calendar rule alone. Check strength with the concrete supplier data or tests required by the specification.
What safety issues should I plan for with formwork?
Plan for falls from height, manual handling, falling objects, collapse during the pour and unstable stacks. Use edge protection, safe access, exclusion zones during the pour and stripping, and a safe work method statement. Keep people clear of under slabs until props are verified. Follow the WHS Regulations.
How do I allow for openings and penetrations?
Deduct large openings from the contact area but add the edge forms around them, since boxing out can cost more than it saves. For small penetrations, keep the area and add blockout items separately. Check the drawings for service penetrations early, since late changes disrupt the formwork layout.
Can this be used for a quote or tender?
Use it as a quick check and a sanity test of your own takeoff. For a quote, measure from the drawings, include all items, apply your cost rates, and check against reuse and labour assumptions. The result is an estimate only, so keep your own records and allow for rounding errors.
When should I get an engineer to design the formwork?
Get an engineer for walls and columns with high pressure, tall pours, SCC, unusual shapes, large soffit spans, props supporting heavy loads or any use of proprietary systems outside supplier tables. A certified design reduces risk on site. EcoDesign can prepare a certified design.
How do I check my result against the drawings?
Take two or three elements by hand, such as one wall, one column and one slab edge, and compare them with the calculator. Then check totals by element type against the drawings schedule. Small differences come from openings, kickers and rounding. A large gap usually means a wrong height or a missed face.