Free tool
Fresh concrete pressure on formwork calculator
Design lateral pressure for wall and column formwork from the rate of rise, temperature and concrete type, with the resulting tie load.
Concept and estimating tool. Check results and get a design by a qualified engineer for construction. Nothing you enter is stored or sent.
How it works
The design pressure is the smaller of the full hydrostatic pressure and the CIRIA formula (CIRIA Report 108, carried into CIRIA C760):
D is the concrete unit weight (kN/m3), H the formwork height and h the vertical pour height (m), R the rate of rise (m/h) and T the concrete temperature at placing (deg C). C1 is 1.0 for walls and 1.5 for columns (both plan dimensions 2 m or less). C2 is 0.3, 0.45 or 0.6 depending on cement type and retarder. Self-compacting concrete is taken as fully hydrostatic. Tie load is the design pressure times the tie's tributary area.
AS 3610.1 sets the requirements for formwork design in Australia; this calculator gives the pressure input to that design, not the design itself.
Questions
Does this replace a formwork design?
No. It gives the design pressure and an indicative tie load. Formwork, ties, walers and soldiers need a design to AS 3610.1 using the supplier's data.
Why does the pressure stop increasing with depth?
Concrete stiffens as it is placed, so below a certain depth the pressure stays constant. The CIRIA method gives that limit from the rate of rise and temperature.
What about vibration and pump-from-below placement?
The method assumes normal internal vibration and placement from the top. Pumping from the base, revibration or external vibrators need full hydrostatic pressure or specific advice.
Module assistant
Concrete pressure assistant
Type a question about this tool or the site work around it. Answers come from 20 questions written and checked by a Chartered Professional Engineer. No AI, nothing is sent or stored.
Top 20 questions
What does the concrete pressure calculator work out?
It estimates the maximum lateral pressure fresh concrete applies to wall or column formwork using the CIRIA R108 / C760 method, then caps it at full hydrostatic pressure. It also converts that pressure into a load per tie from your tie spacing. Use the result to check sheeting, studs, walers and ties against the design of the formwork to AS 3610.1.
What inputs do I need to enter?
You need concrete density (usually about 24 kN/m3), vertical rate of rise in m/h, pour height in m, concrete temperature in deg C, element type (wall or column), and cement type with or without retarder. For ties, add horizontal and vertical tie spacing. Take the cement and retarder details from the mix design or the concrete supplier, not from guesswork.
What are the C1 and C2 coefficients?
C1 depends on the element: 1.0 for walls and 1.5 for columns. C2 depends on cement type and retarder use, taking values of 0.3, 0.45 or 0.6 in the CIRIA method. A slower setting mix has a higher C2 and gives higher pressure. The calculator offers these choices, but confirm the actual cement blend and retarder dose with the supplier.
Why is the pressure limited to D x h?
Fresh concrete cannot push harder than a full fluid column of the same density, so pressure is capped at density x pour height. For tall slow pours the formula can exceed that, and the calculator then reports the hydrostatic value. If the answer equals D x h, the concrete is behaving like a liquid over the full height.
How do I convert my pour rate into rate of rise?
Rate of rise in m/h equals the concrete placed in m3/h divided by the plan area of the pour in m2. For a wall, plan area is length x thickness. Use the real, achievable delivery rate including truck gaps and pump breaks, not the pump's rated output. If the rate varies, check the fastest sustained rate.
How does concrete temperature affect the result?
Cooler concrete sets more slowly, so it stays fluid longer and pressure rises. The method uses K = (36/(T+16))^2, so K increases as temperature falls. Enter the concrete temperature at placing, not the air temperature. In Perth summer pours K is low, and in cold weather it can be much higher.
How is self-compacting concrete (SCC) treated?
The calculator treats SCC as fully hydrostatic, so pressure equals density x pour height from the first lift. SCC is very fluid and does not build internal structure quickly, so rate of rise gives no reduction. Design shutters, ties and bracing for the full head, and confirm any project specific advice with the SCC supplier.
How is the tie load calculated and what are the limits?
Tie load equals pressure x the area each tie supports, which is horizontal spacing x vertical spacing. It is a basic design load for one tie. Check it against the tie's safe working load from the supplier, and remember the calculator does not check ply, studs, walers or bracing. The method also assumes normal vibrated or SCC concrete without unusual additives.
What pour rate should I use to keep pressure down?
Slow the rate of rise or pour in lifts, because pressure grows with rate until the full head is reached. Many sites limit rise to about 1 to 2 m/h for tall walls, but the correct figure comes from the formwork designer's allowable pressure. Work back from that pressure and tell the pump and truck coordinators the maximum rate.
What commonly causes formwork blowouts?
Most blowouts come from pouring faster than the design assumed, missing or wrongly spaced ties, damaged or poorly seated tie nuts, and changes to the mix such as added retarder or a cold load. Poor bracing, base kickers not fixed and unplanned pump surges also contribute. Always get the design assumptions in writing and brief the pour crew.
Does vibration increase the pressure on formwork?
Internal vibration keeps concrete fluid in the zone it reaches, so pressure can approach hydrostatic over the vibrated depth. The CIRIA method assumes normal vibration of the top layer. Do not push the poker deep or re-vibrate old layers, because that fluidises concrete that had started to set. Keep vibration to the placing depth in the design.
Does pumping concrete in from the base change the pressure?
Yes, pumping up from the base can add pressure beyond the normal method because the pump pressure and rapid rise act on the formwork. Treat it as a special case and design for full hydrostatic head plus allowance for surge as advised by the formwork engineer. Do not use the standard rate of rise result without engineering review.
Who must design and check formwork in Australia?
AS 3610.1 Formwork for concrete expects formwork to be designed by a competent person and checked on site before the pour. For tall, complex, high load or proprietary systems, the design should be certified by an engineer, and the as built formwork should match the drawings. The WHS framework also requires risk control for the work. EcoDesign can prepare a certified design.
What should be inspected before the pour starts?
Check the formwork matches the drawings: tie spacing and type, nuts fully engaged, waler and stud sizes, bracing and kickers, and base fixing. Confirm the cleanliness, cover spacers and penetrations, and that the pour plan states the maximum rate of rise. Record a signed pre-pour inspection and fix any defect before the first truck discharges.
Do retarders and slow setting mixes change the design?
Yes. Retarders and high slag or fly ash blends keep concrete fluid longer, so C2 increases and pressure goes up for the same rate of rise. If the supplier changes the mix or adds retarder on a hot day, the design pressure can be exceeded. Get mix details early and have the designer confirm the assumed C2 before the pour.
What if the pour stops partway or trucks are delayed?
Pausing lets the lower concrete stiffen, which reduces pressure on that part, but it can create cold joints if the next layer arrives late. Agree a stop plan beforehand, keep the placing sequence consistent, and avoid a sudden catch up surge that raises the rate of rise. Never send a late batch in quickly to recover time.
Is the tie safe working load the same as its breaking load?
No. Safe working load is the allowable load after a factor of safety, and it is lower than the ultimate or breaking load. Use the supplier's published safe working load for the exact tie, nut, washer and wall thickness, and do not mix components from different systems. Damaged threads, bent ties and reused corroded ties need to be rejected.
Is the sheeting and waler design checked by this calculator?
No. The calculator gives pressure and tie load only. Plywood, studs and walers must be checked separately for bending, shear and deflection under that pressure, using supplier data or an engineer's design. Tie spacing, waler spacing and ply thickness all interact, so changing one on site can overload another.
What safety controls apply during a pour?
The WHS framework requires hazards to be identified and controlled, and formwork and concrete placing are usually covered by a safe work method statement. Set an exclusion zone around the formwork, give the pour supervisor authority to stop work, and have someone watch for bulging, leaks and movement throughout. Keep people off ladders and walers while concrete is rising.
When should I call an engineer rather than use the calculator?
Call an engineer for walls or columns taller than the supplier's standard system limits, SCC, bottom pumped pours, unusual admixtures, cold or very hot conditions, large tie loads, or any doubt about the design assumptions. The calculator is a screening tool, not a certified design. EcoDesign can prepare a certified design.