Free tool
Excavation volume calculator
Bank volume, loose spoil volume and truck loads for pits with batters and for trenches.
Concept and estimating tool. Check results and get a design by a qualified engineer for construction. Nothing you enter is stored or sent.
How it works
Pits with batters use the prismoidal formula V = H/6 (Abase + 4 Amid + Atop), which is exact for a pit with uniform batters. Trenches use the trapezoidal section. Loose volume = bank volume x (1 + bulking).
Questions
What bulking factor should I use?
Bulking depends on the material: sands often 10 to 15 per cent, clays 20 to 40 per cent and rock more. Use project-specific values where available.
Are the batters safe?
The calculator only gives volumes. Batter angles and excavation support must follow geotechnical advice and the WHS requirements for excavation work.
Module assistant
Excavation assistant
Type a question about this tool or the site work around it. Answers come from 20 questions written and checked by a Chartered Professional Engineer. No AI, nothing is sent or stored.
Top 20 questions
How does the excavation volume calculator work for a pit with batters?
It uses the prismoidal formula, V = H/6 x (A1 + 4Am + A2), where A1 is the top area, A2 the base area, Am the area at mid-depth and H the depth. You enter base length and width, depth and batter slope, and it works out the plan size at each level. The result is bank (in-ground) volume.
Why use the prismoidal formula instead of averaging the top and bottom areas?
Averaging top and base areas slightly overestimates a pit with sloping sides, because plan area does not change in a straight line with depth. The prismoidal formula adds the mid-depth area with a weighting of four, which is exact for a straight-sided pit with a constant batter. The difference grows with depth and batter flatness.
How do I enter the batter slope?
Enter it as a horizontal to vertical ratio, for example 1.5 means 1.5 m out for every 1 m of depth, and 0 means vertical sides. Check the input label for the exact format the tool expects. The batter you choose must come from the geotechnical advice, the code of practice or an engineer, not from what is convenient for volume.
How is a trench with a battered side calculated?
Cross-section area is (b + m x d) x d for a symmetrical trench, where b is the base width, d the depth and m the horizontal run per metre of depth on each side. Multiply by trench length for bank volume. Set m to 0 for a vertical-sided trench. Stepped or benched sides need a custom section.
What is the swell or bulking factor and how does the tool use it?
Excavated soil takes up more space than it did in the ground. The tool multiplies bank volume by (1 + swell) to give loose volume, so 100 m3 bank at 30 percent swell becomes 130 m3 loose. The swell percentage depends on the material, so take it from the geotechnical report or your haulage supplier.
How are truck loads worked out?
Truck loads = loose volume divided by the usable capacity of one truck, rounded up. Use the volume the truck can legally and safely carry, not the heaped body size. Wet clay or rock can reach the mass limit before the body is full, so check payload in tonnes as well. Allow extra loads for spillage and over-excavation.
What does the calculator not include?
It does not include working space for formwork or pipe laying, over-excavation, bedding, topsoil strip, pavement removal, shoring thickness, sumps, ramps or stepped sections. It assumes plan shape is rectangular, depth is constant and the batter is uniform. Add allowances for those items yourself, or use survey cross-sections for complex shapes.
How accurate is the volume, and when do I need a survey?
It is a planning and pricing estimate based on simple geometry. Real ground varies, so expect differences from rock, boulders, uneven surfaces and over-dig. For payment quantities, claims or tight haulage budgets, use survey cross-sections or the design model and agree the measurement method in the contract.
When does an excavation count as high risk construction work and need a SWMS?
Under the Work Health and Safety Regulations, work in or near a shaft or trench deeper than 1.5 m is high risk construction work, so a safe work method statement is required before it starts. Other excavation can still need one, for example near underground services or unstable ground. Check the regulations in your state and the project requirements.
What is the difference between battering, benching and shoring?
Battering cuts the sides back to a safe slope. Benching cuts horizontal steps into the sides. Shoring holds the sides up with temporary supports such as trench shields, sheet piles or waling and struts. The right method depends on soil, depth, water, nearby loads and space. Follow the geotechnical advice, the Safe Work Australia Code of Practice Excavation work and any engineer's design.
When do I need shoring or a trench shield, and who designs it?
Use shoring when the sides cannot be safely battered or benched, or when the excavation is deep, in poor ground, wet or near loads. Trench shields are used per the manufacturer's data and the site's conditions, and engineered shoring needs a design by a competent engineer. Installers must follow the design and manufacturer instructions. Do not enter an unsupported trench outside the SWMS.
How far back should spoil, plant and materials be kept from the edge?
Keep them back far enough that their weight does not load the wall, and stop spoil from rolling into the excavation. The distance is set by the SWMS or engineer, and shoring is designed with the surcharge allowed. Site rules often set a minimum clear distance, but the safe distance depends on depth, soil and load, so check it against the actual surcharge.
How do I locate underground services before digging?
Request plans through Before You Dig Australia (BYDA, formerly Dial Before You Dig) before excavating, then confirm positions on site using a locator and non-destructive digging (potholing or vacuum excavation) near the service. Plans are indicative only. Treat every service as live until proved otherwise and follow the asset owner's conditions.
How does groundwater affect an excavation?
Groundwater can soften or collapse sides, lift the base, wash out soil and make shoring work harder. Plan for pumping, sumps, wellpoints or cut-off walls early, based on the geotechnical report. Discharge of water may need approval from the local authority or environmental regulator. Seek an engineer when digging well below the water table.
How often should an excavation be inspected?
Inspect before work starts each shift and after anything that can change stability: rain, vibration, nearby loading, shoring changes or new cracks. A competent person checks sides, shoring, spoil, access, services and water, and records it. Follow the SWMS and permit conditions. Stop work and clear the excavation if you see tension cracks or bulging.
What access, egress and edge protection are needed?
Provide safe ways in and out, such as ladders, steps or ramps, positioned so no worker has a long travel to an exit, as set in the SWMS. Fit barriers or covers at edges where people or plant could fall in, and keep walkways clear. Mark and barricade the area, and control traffic near the edge.
What if the excavation is near an existing building, footing or retaining wall?
Digging near existing structures can undermine them, so do not rely on a standard batter. An engineer should assess the zone of influence, set limits, and design underpinning or shoring if needed. Monitor movement and keep dilapidation records. Stop and get advice if cracks, settlement or water appear.
Can a trench or pit be a confined space or have bad air?
Yes. Deep excavations, pits and trenches near gas, fuel, sewers or fill can hold toxic, flammable or oxygen-deficient air. If the space is a confined space under the WHS Regulations, entry needs a permit, atmospheric testing and rescue arrangements. Test before entry where the SWMS or risk assessment says so, and stop if anything smells or feels wrong.
How do I control excavators, trucks and people around the dig?
Separate people from plant with exclusion zones, a spotter and agreed signals. Keep machines back from the edge and never work under a raised bucket. Use the machine's lifting points and rated hook for any lifting, with a dogman where required. Assume vibration from plant can destabilise the walls. Set traffic management for trucks entering and leaving.
When should I call an engineer for an excavation?
Call one when the depth exceeds standard guidance, the ground is poor or water is present, there are surcharges or structures nearby, shoring is non-standard, or the ground is different to the report. Also stop and ask if sides move. EcoDesign can prepare a certified shoring or temporary works design.