Free tool
Crane lift capacity utilisation calculator
Total lifted load, utilisation of the crane's rated capacity at the working radius, and a typical lift category for planning.
Concept and estimating tool. Check results and get a design by a qualified engineer for construction. Nothing you enter is stored or sent.
How it works
Utilisation = (load + hook block + rigging + other) / rated capacity at the radius, taken from the crane's load chart for the configuration used. Categories shown are typical site criteria and vary between companies.
Questions
Where do I get the rated capacity?
From the manufacturer's load chart for the crane configuration, counterweight, boom length and radius of the lift.
Does this replace a lift plan?
No. Lifts must be planned under AS 2550.1 and your site procedures, including ground bearing, outrigger loads and exclusion zones.
Module assistant
Crane lift assistant
Type a question about this tool or the site work around it. Answers come from 20 questions written and checked by a Chartered Professional Engineer. No AI, nothing is sent or stored.
Top 20 questions
How does the crane lift utilisation calculator work?
Utilisation = total load divided by the crane's rated capacity at the lift radius, shown as a percentage. Total load is the load plus hook block plus rigging. You enter the loads and the capacity read from the load chart, and the tool reports the percentage and a risk category.
What counts in the total load?
Include the item being lifted, the hook block or headache ball, slings, shackles, spreader beams, lifting frames and anything else hanging from the boom tip. Some load charts already deduct the hook block or falls, so check whether the chart is gross or net and match your inputs. If unsure, count everything.
Which radius should I use?
Use the largest horizontal radius reached during the lift, from the slew centre to the centre of the hook, including pick and set positions and the travel path. Boom deflection under load makes the true radius slightly bigger. If between chart values, use the next larger radius, which gives a lower capacity.
Where do I get the rated capacity to enter?
From the manufacturer's load chart for the exact crane set-up: boom length, counterweight, outrigger extent, slew sector, jib and radius. Do not use a nominal crane size such as 100 t. Use the operator's chart for that crane on that day, and check any deductions, and the capacity applies only to that set-up.
What do the utilisation thresholds mean?
Common practice is 75 percent or less as a standard lift, 75 to 90 percent as a critical lift with an engineered lift plan, above 90 percent as high risk needing senior review, and above 100 percent as do not lift. These are widely used guides, not statutory limits, and your project, client or crane company may be stricter.
Does the tool consider wind, ground conditions or dynamic effects?
No. It only compares weights with capacity. Wind on the load, ground bearing, slew speed, travel, boom deflection and out-of-level set-up are separate checks for the lift plan. The result is a first screening, not approval to lift. Use the manufacturer's data and a qualified person to cover these effects.
Can I use the tool for tandem or multi-crane lifts?
No. It is for a single crane lifting a known load. In tandem lifts the share of load on each crane changes with geometry and movement, so each crane needs its own check, with reduced loadings as set by an engineered plan. Use a qualified lift engineer and the crane supplier for these.
Is a passing result a lift plan or approval to lift?
No. It is a quick screening of weights against capacity. A lift plan also covers ground, set-up, rigging, exclusion zones, weather, roles, communication and contingencies. Approval comes from the competent person in charge following the lift plan and permit system, using the crane's load chart and manufacturer data.
What should a lift plan include and when is one needed?
A lift plan covers the load details, crane and configuration, radius, ground, rigging, exclusion zones, signals, weather limits, roles and emergency steps. AS 2550 Cranes, hoists and winches - Safe use and the WHS framework expect lifts to be planned. Complex, critical and tandem lifts need a documented plan reviewed by the competent person.
How do I check ground bearing and outrigger pads?
Get the outrigger reaction from the crane manufacturer, divide by the pad area to get pressure and compare with the allowable ground bearing in kPa from a geotechnical source or engineer. Use timber or steel mats to spread load, and check for services, trenches, backfill and slopes. Do not assume the ground is firm.
What are the wind limits for lifting?
Wind limits come from the crane manufacturer and the load itself, because large, light or flat loads act as sails. Use the site anemometer or forecast and stop when conditions are beyond the chart, or the lift plan limit. The operator can stop any lift. Do not use a generic speed without checking the crane manual.
How do I set exclusion zones for a lift?
Barricade the area under the load path and the swing radius of the boom and counterweight, including the tail swing. No one should be under a suspended load. Use signage and a person to control access, and plan the path so the load does not pass over people, occupied buildings or roads unless properly controlled.
What are the roles of the crane operator, dogman and rigger?
The operator controls the crane and can refuse any unsafe lift. The dogman slings the load and directs the operator with signals. The rigger sets up rigging and gear. One designated person gives signals at a time, except stop. The lift supervisor holds the plan and confirms everyone knows their role.
What licences are required for crane work?
Under the WHS Regulations (in WA the Work Health and Safety (General) Regulations 2022), operators need a high risk work licence for the class of crane. Dogging and rigging licences are needed for slinging and rigging work, in appropriate classes. Check the licence, class and expiry on site, and that it matches the crane and task.
What must I do when lifting near powerlines?
Treat all overhead lines as live. Identify them in the lift plan, contact the network operator for advice and, where needed, isolation or a safe approach distance. Required distances depend on voltage and jurisdiction, so check with the operator and regulator. Use a spotter, and plan so that no part of the crane or load can reach the lines.
What extra controls apply to tandem lifts?
Tandem lifts need an engineered lift plan because load share between cranes changes with positions. Capacities are derated per the plan and crane maker, one person must coordinate both operators, and movements must be slow and synchronised. Avoid tandem lifts where a single larger crane is practical. Seek a qualified engineer.
What inspections and records are needed for the crane and gear?
The crane should have current periodic inspection and maintenance records, with the operator doing a pre-start check each shift. Lifting gear needs tagging and periodic inspection by a competent person. Keep the lift plan, licences, inspection records and permits on site. Follow AS 2550 and the project's requirements.
Why do a test lift?
A test lift raises the load slightly off the ground and holds it to check the weight, balance, rigging, brakes, set-up and ground behaviour before the main movement. If the crane or ground moves or the load is heavier than expected, lower it and recheck. A test lift is a good control, but does not replace calculation.
How do I confirm the weight of the load?
Use verified data: certified drawings, supplier weights, weighbridge or load cell. Do not guess from size. Account for concrete, water, fittings and packaging, and add a margin for unknowns. An unknown or heavier load is a common reason lifts exceed capacity, so verify before the lift plan is finalised.
When should I involve an engineer in a crane lift?
Involve one for critical lifts above 75 percent, tandem lifts, poor or unknown ground, lifts near buildings or services, unusual rigging or high consequence loads. They can check ground bearing, structures and lift points. EcoDesign can prepare a lift study or a certified design.